M&C Review


COUNCIL ACTION:  Approved on 3/19/2019 

DATE: 3/19/2019 REFERENCE NO.: **C-29061 LOG NAME: 21WRMC RICHARDSON BASS STALLS REPLACEMENT
CODE: C TYPE: CONSENT PUBLIC HEARING: NO
SUBJECT:  

Authorize Execution of a Construction Contract with FPI Builders, LLC, in the Total Amount of $720,754.00, Including 7.5 Percent for the Owner's Construction Contingency Allowance, for Richardson Bass Stall Replacement Project at Will Rogers Memorial Center, and Provide for Administrative Costs for a Total Project Amount of $916,552.00 (COUNCIL DISTRICT 7)


RECOMMENDATION:

It is recommended that the City Council authorize execution of a construction contract with FPI Builders, LLC, in the total amount of $720,754.00, including 7.5 percent for the Owner's Construction Contingency Allowance, for Richardson Bass Stall Replacement Project at Will Rogers Memorial Center, and provide for administrative costs, for a total project amount of $916,552.00.

 
DISCUSSION:

The Purpose of this M&C is to authorize execution of a construction contract with FPI Builders, LLC, in the total amount of $720,754.00, including 7.5 percent for the Owner's Construction Contingency Allowance, for Richardson Bass Stall Replacement Project at the Will Rogers Memorial Center and to provide for associated administrative costs.  This project, approved in the FY2017 CIP, will remove existing asphalt pavement and replace with concrete.  It will also remove and replace the electrical outlets serving existing stall areas.  The contractor will install owner furnished stalls panels to complete the remodel.

The City issued a Request for Proposals (RFP) in the Fort Worth Star-Telegram on November 8, 2018 and November 15, 2018, and received nine proposals on December 13, 2018 for the project from general construction contractors.  Three of these firms provided the required "Post Proposal–Pre Award Submittals" to be further evaluated by the City.  These proposals were reviewed by members of the Public Events Department, the M/WBE Office and the Property Management Department and were evaluated for best value based on the criteria set forth in the Request for Proposals.  The selection team recommends award the construction contract to FPI Builders, LLC.  The following table provides a summary of the scoring.

Criteria

FPI Builders, LLC

Morales Construction Services, Inc.

MSB Construction Services, Inc.

Proposed Price

58

60

59

M/WBE

5

6

2

Proposed Schedule

9

9

10

Reputation/Experience

9

7

3

Past Relationship with City of Fort Worth

9

5

5

TOTAL

90

87

79


The overall project costs are listed in the table below:

DROP OFF STATION IMPROVMENTS

TOTALS

Design Contract

$86,803.00

Construction Contract (including 7.5 percent of Owner's Construction Contingency Allowance)

$720,754.00

Combined Project Administration Costs (Project Management, Contingency, FFE, Etc.)

$108,995.00

PROJECT TOTAL

$916,552.00




In accordance with Chapter 7, Article III, Section 7-47, Section 109.2.1 of the City Code, Building and Trade Permit Fees and are waived for this project.

M/WBE OFFICE - FPI Builders, LLC, is in compliance with the City's BDE Ordinance by committing to 8% MBE participation on this project. The City's MBE goal on this project is 8%.

The Will Rogers Memorial Center is located in Council District 7.
 
FISCAL INFORMATION/CERTIFICATION:

The Director of Finance certifies that funds are available in the current capital budget, as appropriated, of the Culture & Tour DFW Rev Sh Cap Fund. Prior to an expenditure being incurred, the department has the responsibility to validate the availability of funds.

TO
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

FROM
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

Submitted for City Manager's Office by:
Jay Chapa (5804)
Originating Department Head:
Roger Venables (6334)
Additional Information Contact:
Brian Glass (8088)

 
 
ATTACHMENTS
  FPI Executed HB 1295_Redacted.pdf
  WRMC Richardson Bass.pdf