DATE: | 3/19/2019 | REFERENCE NO.: | **C-29067 | LOG NAME: | 60LALSFMA1-FNI |
CODE: | C | TYPE: | CONSENT | PUBLIC HEARING: | NO |
SUBJECT: | Authorize Execution of Amendment No. 1 in the Amount of $229,755.00 to City Secretary Contract No. 50312, an Engineering Agreement with Freese and Nichols, Inc., for a Revised Contract Amount of $3,329,116.00 for Design of the Lake Arlington Lift Station and Force Main, Located in the Carver Heights East and Enchanted Bay Neighborhoods (COUNCIL DISTRICT 5) |
RECOMMENDATION: | ||||||||||||
It is recommended that the City Council authorize execution of Amendment No. 1 to City Secretary Contract No. 50312, an Engineering Agreement with Freese and Nichols, Inc., in the amount of $229,755.00 for a revised contract in the amount of $3,329,116.00 for Design of the Lake Arlington Lift Station and Force Main, Located in the Carver Heights East and Enchanted Bay Neighborhoods. (City Project No. 100995) |
||||||||||||
DISCUSSION: | ||||||||||||
On January 30, 2018, Mayor and Council Communication (M&C C-28566) the City Council authorized the execution of an Engineering Agreement with Freese and Nichols, Inc., in the amount of $3,099,361.00 for the preparation of plans and specifications for the Lake Arlington Lift Station and Force Main Project. |
||||||||||||
FISCAL INFORMATION/CERTIFICATION: | ||||||||||||
The Director of Finance certifies that funds are available in the Water and Sewer Capital Projects 2018 Bond Fund for Lake Arlington Lift Station and Force Main Project.
|
|
|||||||||||||||||||||
|
Submitted for City Manager's Office by: |
|
Originating Department Head: |
|
Additional Information Contact: |
|
|
ATTACHMENTS |
60LALSFM FNI MAP.pdf |
60LALSFMA1 FNI Form 1295 2019-440147_Redacted.pdf |