M&C Review


COUNCIL ACTION:  Approved on 3/19/2019 - Ordinance No. 23594-03-2019

DATE: 3/19/2019 REFERENCE NO.: **G-19507 LOG NAME: 20PROJECT FUNDING REDISTRIBUTION FOR STREET IMPROVEMENTS
CODE: G TYPE: CONSENT PUBLIC HEARING: NO
SUBJECT:   Adopt Appropriation Ordinance Redistributing the Existing Project Funds Among Council District 5 Streets Improvement Projects (COUNCIL DISTRICT 5)

RECOMMENDATION:

It is recommended that the City Council adopt the attached ordinance redistributing $363,292.80 of previously appropriated funds among City Project Nos. 100732, 100739, 100740, 100741, 100743, and 100744 in the Street Improvements Supplement and Street Improvements 2008 Funds.

 
DISCUSSION:

This Mayor and Council Communication (M&C) is to reallocate previously appropriated funding between various street improvements projects in Council District 5, with the revised funding by project shown below.  

On December 13, 2016, the City Council appropriated funds from a cancelled project (M&C G-18738) to nine other street improvement projects in Council District 5, with the appropriations based on anticipated costs of each project.

As the projects have progressed, TPW finds the total funding to be sufficient, however six of the projects are out of balance. Certain projects are underfunded for various reasons such as increased construction costs, changes in the contracting method, project management, and third party inspection costs. TPW recommends redistributing the appropriated funds from the projects that are under budget to allow for completion of the remaining projects. Adoption of the attached ordinance will adjust the remaining appropriations in various projects without changing the cumulated total.

The projects at issue listed below identifies the original appropriation amount (based on planned estimates for the construction cost) and the proposed adjustments.

Project Number

Project Name

Original Funding

Current Funding

Revised Funding Amount

100744

Pate Drive (Coleman to Berry)

$700,000.00

   $700,000.00

$393,707.20

100741

Elgin St (Dillard to Stalcup)

$335,000.00

   $335,000.00

$461,763.30

100740

Grayson St (S Cravens to Casa Loma)

$170,000.00

   $170,000.00

$194,493.30

100739

Casa Loma (N Terminus to S Terminus)

$50,000.00

    $50,000.00

$64,474.20

100743

Handley Drive (Lancaster to Meadowbrook)

$1,939,000.45

$1,939,000.45

$1,882,000.45

100732

Liberty Street

$100,000.00

   $100,000.00

$297,562.00

*

Totals

$3,294,000.45

$3,294,000.45

$3,294,000.45


Completion of these projects will have no impact on the Transportation and Public Works annual operating budget nor on the Water Department's operating budget when completed. Construction is already in progress.

The project is located in COUNCIL DISTRICT 5.  

This M&C does not request approval of a contract with a business entity.
 
FISCAL INFORMATION/CERTIFICATION:

The Director of Finance certifies that, when the appropriations ordinance is approved, funds will be available in the current capital budget as appropriated for Street Improvements Supplement and Street Improvements 2008 Funds.

TO
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

FROM
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

Submitted for City Manager's Office by:
Susan Alanis (8180)
Originating Department Head:
Steve Cooke (5134)
Additional Information Contact:
Lane Zarate (7802)

 
 
ATTACHMENTS
  REDISTRIBUTION AO19 39406_.docx