M&C Review


COUNCIL ACTION:  Approved on 2/12/2019 

DATE: 2/12/2019 REFERENCE NO.: **C-29035 LOG NAME: 20SW EXTENSION TEMPORARY CLOSURE OF BRENNAN AVENUE
CODE: C TYPE: CONSENT PUBLIC HEARING: NO
SUBJECT:   Authorize Extension of Temporary Closure of Brennan Avenue from Guenther Avenue to Peak Street from February 24, 2019 through April 30, 2019 to Allow for the Completion of Construction Improvements for Brennan Avenue (COUNCIL DISTRICT 2)

RECOMMENDATION:

It is recommended that the City Council authorize the extension of the temporary closure of Brennan Avenue from Guenther Avenue to Peak Street from February 24, 2019 through April 30, 2019 to allow for the completion of construction of the culvert under Brennan Avenue.

 
DISCUSSION:

Klutz Construction requests the temporary closure of Brennan Avenue from Guenther Avenue to Peak Street be extended from February 24, 2019 through April 30, 2019. The original closure from October 24 to February 24 was approved through Mayor and Council Communication (M&C G-19403) on October 23, 2018. During construction, low concentrations of soil contaminants were discovered onsite which required removal from the ground and caused a 33-day delay in the construction schedule.

Additionally, during construction, staff determined that the water line construction should occur during the temporary road closure for public safety reasons. The water line construction duration was 30 days. Due to these schedule impacts, the contractor has requested the closure be extended to April 30, 2019.

This road closure is located in COUNCIL DISTRICT 2.

This M&C does not request approval of a contract with a business entity.

 
FISCAL INFORMATION/CERTIFICATION:

The Director of Finance certifies that this action will have no material effect on City funds.

TO
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

FROM
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

Submitted for City Manager's Office by:
Susan Alanis (8180)
Originating Department Head:
Steve Cooke (5134)
Additional Information Contact:
Mike Bennett (7891)

 
 
ATTACHMENTS