COUNCIL ACTION:  Approved on 3/19/2019 

DATE: 3/19/2019 REFERENCE NO.: **G-19506 LOG NAME: 20MARINE CREEK PARKWAY CHANGE ORDER NO. 5
CODE: G TYPE: CONSENT PUBLIC HEARING: NO
SUBJECT:   Authorize Execution of Change Order No. 5 to City Secretary No. 48125 with Jackson Construction, Ltd., in the Amount of -$472,485.70 for the Marine Creek Parkway and Old Decatur Road Project, thereby Decreasing the Total Incentive Based Contract Amount to $11,212,928.53 (COUNCIL DISTRICT 2)

RECOMMENDATION:

It is recommended that the City Council authorize execution of Change Order No. 5 to City Secretary No. 48125 with Jackson Construction, Ltd., in the amount of -$472,485.70 for the Marine Creek Parkway and Old Decatur Project, thereby decreasing the total contract amount to $11,212,928.53 (City Project No. 02506/02304).

 
DISCUSSION:

On June 28, 2016, Mayor and Council Communication (M&C C-27816), the City Council authorized award of a construction contract with Jackson Construction, Ltd., in the amount up to $11,531,299.00, inclusive of potential incentives, for the construction of improvements to Marine Creek Parkway/Old Decatur Road from south of McLeroy Boulevard to north of Grayson Road, Cromwell Marine Creek Road from Old Decatur Road to Marine Creek Parkway and Longhorn Road from Old Decatur Road to Marine Creek Parkway and construction of Northside II 48-inch water Transmission Main Phase 2, Part 3.  

The following is a summary of the Change Orders to date:  

-

Amount

Days

M&C No.

Approved

Description

Original Contract

$11,426,299.00

480

C-27816

6/28/2016

-

Change Order #1

$321,470.42

0

C-28572

2/6/2018

EMSISD School water and sewer

Change Order #2

$55,822.40

0

C-28571

2/6/2018

Added median opening

Change Order #3

-$99,555.37

124

Administrative

-

Landscaping design changes, Cromwell RAB pavement, Over/Under

Change Order #4

-$18,622.22

0

Administrative

-

Partial Reconciliation

Change Order #5

-$472,485.70

-

Pending

-

Final Reconciliation

Totals

$11,212,928.53

604

-

-

-

Change Order No. 5 in the amount of -$472,485.70 reconciles the final quantity over and underruns of which the difference will be reallocated to street improvements and  water improvements for the Marine Creek Parkway and Old Decatur Road Project construction project. This provides for processing final close out of the project and construction contract. The final inspection was performed on June 6, 2018.

This project is located in COUNCIL DISTRICT 2.

 
FISCAL INFORMATION/CERTIFICATION:

The Director of Finance certifies that upon approval of the above recommendation funds will be available in the current capital budget as appropriated of the 2014 Bond Program Fund and the Water and Sewer Bond 2017A Fund.

TO
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

FROM
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

Submitted for City Manager's Office by:
Susan Alanis (8180)
Originating Department Head:
Steve Cooke (5134)
Additional Information Contact:
Wilma Smith (8765)

 
 
ATTACHMENTS
  Form 1295 Jackson Const. Marine Ck_Redacted.pdf
  Map Marine Creek C.O. 5.pdf