On June 28, 2016, Mayor and Council Communication (M&C C-27816), the City Council authorized award of a construction contract with Jackson Construction, Ltd., in the amount up to $11,531,299.00, inclusive of potential incentives, for the construction of improvements to Marine Creek Parkway/Old Decatur Road from south of McLeroy Boulevard to north of Grayson Road, Cromwell Marine Creek Road from Old Decatur Road to Marine Creek Parkway and Longhorn Road from Old Decatur Road to Marine Creek Parkway and construction of Northside II 48-inch water Transmission Main Phase 2, Part 3. The following is a summary of the Change Orders to date: - | Amount | Days | M&C No. | Approved | Description | Original Contract | $11,426,299.00 | 480 | C-27816 | 6/28/2016 | - | Change Order #1 | $321,470.42 | 0 | C-28572 | 2/6/2018 | EMSISD School water and sewer | Change Order #2 | $55,822.40 | 0 | C-28571 | 2/6/2018 | Added median opening | Change Order #3 | -$99,555.37 | 124 | Administrative | - | Landscaping design changes, Cromwell RAB pavement, Over/Under | Change Order #4 | -$18,622.22 | 0 | Administrative | - | Partial Reconciliation | Change Order #5 | -$472,485.70 | - | Pending | - | Final Reconciliation | Totals | $11,212,928.53 | 604 | - | - | - |
Change Order No. 5 in the amount of -$472,485.70 reconciles the final quantity over and underruns of which the difference will be reallocated to street improvements and water improvements for the Marine Creek Parkway and Old Decatur Road Project construction project. This provides for processing final close out of the project and construction contract. The final inspection was performed on June 6, 2018. This project is located in COUNCIL DISTRICT 2. |