COUNCIL ACTION:  Approved on 8/14/2018 

DATE: 8/14/2018 REFERENCE NO.: **C-28792 LOG NAME: 21NORTH SERVICE CENTER - CHANGE ORDER NO. 10
CODE: C TYPE: CONSENT PUBLIC HEARING: NO
SUBJECT:  

Authorize Execution of Change Order No. 10 in the Amount of $13,324.42 to City Secretary Contract No. 46976 with the Ridgemont Company d/b/a Ridgemont Commercial Construction, Inc., for a Revised Contract Amount of $26,583,962.42 for the North Service Center (2014 Bond Program) (COUNCIL DISTRICT 7)


RECOMMENDATION:

It is recommended that the City Council authorize the execution of Change Order No. 10 in the amount of $13,324.42 to City Secretary Contract No. 46976 with the Ridgemont Company d/b/a Ridgemont Commercial Construction, Inc., for a revised contract amount of $26,583,962.42 for the North Service Center.

 
DISCUSSION:

The purpose of Change Order No. 10 is to finalize the contract amount, pay for utilities from the time of substantial completion to the time the City took over the utility accounts, and to add an electrical outlet for a welder in the fleet building.  Change Order No. 10 adds $13,324.42 to the contract.  

On July 21, 2015, the City Council authorized execution of a Construction Manager-At-Risk Contract with the Ridgemont Company d/b/a Ridgemont Commercial Construction, Inc., in an amount not to exceed $25,462,398.00 for the North Service Center, Phases I and II, Field Operations Services Center.  Change Order No. 10 adds $13,324.42 to the contract.  Change Order Nos. 1, 2, 3, 4, 5, 6, 7, 8 and 9 increased the contract amount by $1,108,240.00.  Including Change Order No. 10, the combined increase to the contract is $1,121,564.42 or 4.4 percent.

The combined value of Change Orders No. 1 through No. 4 exceeded $100,000.00; therefore, Change Order No. 4 required City Council approval (M&C C-28102, February 7, 2017).  The combined value of Change Orders No. 5, 6 and 7 exceeded $100,000.00; therefore, Change Order No. 7 required City Council approval (M&C C-28508, December 12, 2017). The combined value of Change Orders 8, 9, and 10 will exceed $100,000.00; therefore, Change Order No. 10 will require City Council approval.

A portion of this project will include 2014 Bond Funds.  Available resources within the General Fund will be used to provide interim financing for these expenses until debt is issued.  Once debt associated with this project is sold, bond proceeds will reimburse the General Fund in accordance with the statement expressing official intent to reimburse, that was adopted as part of the ordinance canvassing the bond election (Ordinance No. 21241-05-2014) and subsequent actions.

M/WBE OFFICE - Ridgemont Commercial Construction, Inc., is in compliance with the City's BDE Ordinance by committing to an overall 30 percent MBE participation on the CMAR project inclusive of this Change Order No. 10.  The City's MBE goal on this CMAR is 30 percent.


The construction started in December 2015 and was completed in April 2018.  

The project is physically located in COUNCIL DISTRICT 7, and serves all Fort Worth residents in ALL COUNCIL DISTRICTS.

 
FISCAL INFORMATION/CERTIFICATION:

The Director of Finance certifies that upon approval of the above recommendation, funds will be available as appropriated of the Specially Funded Projects fund and the 2014 Bond Program. (City Project No. C02105)

TO
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

FROM
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

Submitted for City Manager's Office by:
Jay Chapa (5804)
Originating Department Head:
Steve Cooke (5134)
Additional Information Contact:
Brian Glass (8088)

 
 
ATTACHMENTS
  Form 1295-Certificate of Interested Parties.pdf
  North Serv Ctr CMAR Location Map 20feb15.pdf