COUNCIL ACTION: Approved on 6/26/2018 - Ordinance No. 23282-06-2018 | |||||
DATE: | 6/26/2018 | REFERENCE NO.: | **C-28748 | LOG NAME: | 55FTW MEACHAM ADMINISTRATION PARKING IMPROVEMENTS |
CODE: | C | TYPE: | CONSENT | PUBLIC HEARING: | NO |
SUBJECT: | Authorize Execution of a Construction Agreement with Cole Construction, Inc., in an Amount Up to $469,800.00 for Construction of Meacham Administration Building Parking Improvements at Fort Worth Meacham International Airport and Adopt Appropriation Ordinance (COUNCIL DISTRICT 2) |
RECOMMENDATION: | ||||||||||||||||||||
It is recommended that the City Council: 1. Authorize the use of revenue derived from mineral leases on City-owned airports in an amount up to $469,800.00 for the construction of Meacham Administration Building Parking Improvements at Fort Worth Meacham International Airport; 2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations of the Aviation Gas Lease Capital Project Legacy Fund in the amount of $469,800.00; and 3. Authorize execution of a Construction Agreement with Cole Construction, Inc., in an amount not to exceed $469,800.00 for the construction of Meacham Administration Building Parking Improvements at Fort Worth Meacham International Airport. |
||||||||||||||||||||
DISCUSSION: | ||||||||||||||||||||
On December 5th, 2017, Mayor and Council Communication (M&C C-28493) the City Council authorized the execution of an Engineering Services Agreement with Garver, LLC (Garver), in the amount of $163,920.00 for the design and construction management services of Meacham Administration Building Parking Improvements at Fort Worth Meacham International Airport (Airport). The project will provide 80 additional parking spaces which will be located parallel to Main Street, directly east of Hangar 4N and southeast of the main Meacham Administration Building parking lot. The overall cost for construction of this project is expected to be:
The construction portion of the project was advertised for bid in the Fort Worth Star-Telegram on April 20, 2018 and April 27, 2018. On May 21, 2018, six Offerors submitted proposals, and on May 30, 2018, the contract was awarded to Cole Construction, Inc., based on the lowest bid received. The following six proposals were received (Total Bid):
Cole Construction, Inc. is in compliance with the City's BDE Ordinance by committing to 15 percent MBE participation on this project. The City's MBE goal on this project is 15 percent. ADVISORY BOARD APPROVAL – On May 18, 2017, the Aviation Advisory Board voted to recommend that the City Council approve the Aviation Department's Five-Year Capital Improvement Plan. The addition of parking at the Aviation Administration building was a part of the approved plan. |
||||||||||||||||||||
FISCAL INFORMATION/CERTIFICATION: | ||||||||||||||||||||
The Director of Finance certifies that upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the current capital budget, as appropriated, of the Aviation Gas Lease Capital Projects Legacy Fund. |
|
|||||||||||||||||||||
|
Submitted for City Manager's Office by: |
|
Originating Department Head: |
|
Additional Information Contact: |
|
|
ATTACHMENTS |
55FTW MEACHAM ADMINISTRATION PARKING IMPROVEMENTS_55_AO_18.docx |
Form 1295 - Meacham Administration Parking Improvements 101239.pdf |
MC Map Admin Parking.pdf |