M&C Review


COUNCIL ACTION:  Approved on 1/23/2018 - Ordinance No. 23081-01-2018

DATE: 1/23/2018 REFERENCE NO.: **C-28541 LOG NAME: 60SSR89CO1-ARK
CODE: C TYPE: CONSENT PUBLIC HEARING: NO
SUBJECT:   Authorize Execution of Change Order No. 1 in the Amount of $164,000.00 and the Addition of 87 days to City Secretary Contract No. 48579 with Ark Contracting Services LLC, for a Revised Contract Amount of $2,474,607.00 for Sanitary Sewer Rehabilitation Contract 89 and Adopt Appropriation Ordinance (COUNCIL DISTRICTS 3 and 7)

RECOMMENDATION:

It is recommended that the City Council:

1.  Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Sewer Capital Fund – Legacy in the amount of $174,000.00 from available funds; and

2.  Authorize the execution of Change Order No. 1 to City Secretary Contract No. 48579 with ARK Contracting Services, LLC, in the amount of $164,000.00 and the addition of 87 calendar days for Sanitary Sewer Rehabilitation, Contract 89. (City Project No. C02381)

 
DISCUSSION:

On December 6, 2016, Mayor and Council Communication (M&C C-28023) the City Council authorized a contract with Ark Contracting Services, LLC, in the amount of $2,310,607.00 for Sanitary Sewer Rehabilitation, Contract 89.

Change Order No. 1 will provide for the replacement of the severely deteriorated sanitary sewer main located between Park Ridge Boulevard and Mission Street from Lubbock Street, southwesterly 770 feet. In addition to the change order amount, $10,000.00 is required for project management and inspection. Construction is estimated to be complete by March 30, 2018.

M/WBE OFFICE:  Ark Contracting Services, LLC, agrees to maintain its initial M/WBE commitment of five percent  that it made on the original contract and extend and maintain that same M/WBE commitment of five percent on all prior change orders up to and inclusive of this Change Order No. 1. Therefore Ark Contracting Services, LLC, remains in compliance with the City's M/WBE Ordinance and attests to its commitment by its signature on the Acceptance of Previous M/WBE Commitment from executed by an authorized representative of its company.

The project is located in COUNCIL DISTRICTS 3 and 7.

 
FISCAL INFORMATION/CERTIFICATION:

The Director of Finance certifies that upon approval of the above recommendations and adoption of the attached appropriation ordinance funds will be available in the current capital budget, as appropriated, of the Sewer Capital Fund - Legacy. The Fiscal Year 2018 Water Operating Budget includes appropriations of $29,022,689.00 for the purpose of providing Pay-As-You-Go funding for Sewer Capital Projects. After this transfer for Fiscal Year 2018, the balance will be $18,783,497. Appropriations for Sanitary Sewer Rehabilitation, Contract 89. Project by Fund will consist of the following:

FUNDExisting AppropriationsAdditional AppropriationsProject Total*
Sewer Capital Fund - Legacy 59607$2,882,432.00$174,000.00$3,056,432.00
Project Total$2,882,432.00$174,000.00$3,056,432.00
*Numbers rounded for presentation purposes.

TO
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

FROM
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

Submitted for City Manager's Office by:
Jay Chapa (5804)
Originating Department Head:
Kenneth Morgan (8246)
Additional Information Contact:
Walter Norwood (5026)

 
 