COUNCIL ACTION:  Approved on 1/23/2018 - Ordinance Nos. 23087-01-2018 & 23088-01-2018

DATE: 1/23/2018 REFERENCE NO.: C-28543 LOG NAME: 202014 CIP YEAR 3 CONTRACT 9-ARK CONTRACTING
CODE: C TYPE: NON-CONSENT PUBLIC HEARING: NO
SUBJECT:   Authorize Execution of Contract with Ark Contracting Services, LLC, in the Amount of $4,101,683.50 for 2014 CIP Year 3 Contract No. 9, Combined Street Paving Improvements, Water and Sanitary Sewer Main Improvements and Adopt Appropriation Ordinances (2014 BOND PROGRAM) (COUNCIL DISTRICTS 8 and 9 )

RECOMMENDATION:

It is recommended that the City Council:

1.  Adopt the attached appropriation ordinances increasing estimated receipts and appropriations in the Water Capital Fund in the amount of $1,420,467.00 from available funds and in the Sewer Capital Fund - Legacy in the amount of $440,648.00 from available funds; and

2.  Authorize execution of a contract with Ark Contracting Services, LLC, in the amount of $4,101,683.50 for 2014 CIP Year 3 Contract No. 9, Combined Street Paving Improvements, Water and Sanitary Sewer Main Improvements (City Project No. 02696).

 
DISCUSSION:

This Mayor and Council Communication is to authorize a construction contract for water, sanitary sewer and paving improvements on approximately 1.68 lane miles located in the Historic Southside, United Riverside, Oakhurst and Bluebonnet Hills Place neighborhoods and on the streets below:

    

Street

From

To

Bluebonnet Circle

S. University Drive

S. University Drive

Rouse Street

N. Sylvania Avenue

Emma Street

Smilax Avenue

SW Cul-de-Sac

NE Cul-de-Sac

Kentucky Avenue

Broadway Avenue

E. Tucker Street

In addition to the above improvements, the existing sanitary sewer main north and parallel to Bluebonnet Circle from S. University Drive to Rogers Avenue will be rehabilitated as part of this project.

The Transportation and Public Works Department's participation on this contract is $2,552,605.50 which is available from the Street Improvement Certificate of Obligation (COs) Residuals Fund and 2014 Bond Program Funds (City Project No. C02696).  The Water Department's participation on this contract is $1,549,078.00 available in the Water Capital Fund and Sewer Capital Fund-Legacy of the project (City Project No. C02696).

The project was advertised for bid on October 19, 2017 and October 26, 2017 in the Fort Worth Star-Telegram.  On November 30, 2017, the following bids were received:



Bidder

Amount

Time of Completion

Ark Contracting Services, LLC

$4,101,683.50

365 Calendar Days

Jackson Construction, Ltd

$4,105,806.00

         

Fort Worth Civil Constructors, LLC

$4,381,271.93

            

Stabile & Winn, Inc.

$5,020,116.25

      


Available resources within the General Fund will be used to provide interim financing until debt is issued.  Once debt associated with the project is sold, bond proceeds will reimburse the General Fund, in accordance with the statement expressing Official Intent to Reimburse that was adopted as part of the ordinance canvassing the bond election (Ordinance No. 21241-05-2014) and subsequent actions taken by the Mayor and Council.

In addition to the contract amount, $623,218.00 (Water: $168,954.00; Sewer: $65,629.00; Paving: $388,635.00) is required for City project delivery services and $205,084.00 (Water:  $59,596.00; Sewer:  $17,858.00; Paving:  $127,630.00) is provided for project contingencies.

The sanitary sewer component of this project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.

This project will have no impact on the Transportation and Public Works' annual operation budget nor on the Water Department's operating budget when completed. Construction is expected to start in March 2018 and be completed by March 2019.

M/WBE OFFICE - Ark Contracting Services, LLC, is in compliance with the City's BDE Ordinance by committing to one percent MBE participation and documenting good faith effort.  Ark Contracting Services, LLC, identified several subcontracting and supplier opportunities.  However, the MBE's contacted in the areas identified did not respond or did not submit the lowest bids.  The City's MBE goal on this project is 10 percent.

The project is located in COUNCIL DISTRICTS 8 and 9.

 
FISCAL INFORMATION/CERTIFICATION:

The Director of Finance certifies that funds are available in the current capital budget as appropriated of Street Improvement COs Residuals and the 2014 Bond Program.  In addition, upon approval of the above recommendations and adoption of the attached appropriation ordinances, funds will be available in the current capital budget, as appropriated, of the Water Capital Projects Fund and Sewer Capital Fund-Legacy.  The Fiscal year 2018 Water Operating Budget includes appropriations of $29,069,236.00 for the purpose of providing Pay-As–You-Go funding for Water Capital Projects.  After this transfer for Fiscal Year 2018, the balance will be $21,078,250.00.  The Fiscal Year 2018 Water Operating Budget includes appropriations of $29,022,689.00 for the purpose of providing Pay-As-You-Go funding for Sewer Capital Projects.  After this transfer for Fiscal Year 2018, the balance will be $22,240,791.00.














TO
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

FROM
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

Submitted for City Manager's Office by:
Jay Chapa (5804)
Originating Department Head:
Douglas Wiersig (7801)
Additional Information Contact:
Mary Hanna (5565)

 
 
ATTACHMENTS
  202014 CIP YEAR 3 CONTRACT 9-ARK CONTRACTING _59601_AO18R.docx
  202014 CIP YEAR 3 CONTRACT 9-ARK CONTRACTING _59607_AO18R.docx
  202014CIPYEAR3CONTRACT9-ARK_1295 form.pdf
  MC Map - 202014CIPYEAR3CONTRACT9-ARK1.pdf
  MC Map - 202014CIPYEAR3CONTRACT9-ARK2.pdf
  MC Map - 202014CIPYEAR3CONTRACT9-ARK3.pdf
  MC Map - 202014CIPYEAR3CONTRACT9-ARK4.pdf