COUNCIL ACTION:  Approved on 2/13/2018 

DATE: 2/13/2018 REFERENCE NO.: **C-28577 LOG NAME: 20GARDEN ACRES BRIDGE AMENDMENT 6
CODE: C TYPE: CONSENT PUBLIC HEARING: NO
SUBJECT:   Authorize Execution of Amendment No. 6 to City Secretary Contract No. 43361, an Engineering Services Agreement with URS Corporation n/k/a AECOM for the Widening of Garden Acres Bridge Over IH-35W, in the Amount of $44,784.00 for Additional Construction Phase Services Thereby Increasing the Contract Amount to $977,489.53 (COUNCIL DISTRICT 6)

RECOMMENDATION:

It is recommended that the City Council authorize the execution of Amendment No. 6 to City Secretary Contract No. 43361, an Engineering Services Agreement with URS Corporation n/k/a AECOM, in the not-to-exceed amount of $44,784.00 for additional Construction Phase Services, thereby increasing the contract amount to $977,489.53 (C01802).

 
DISCUSSION:

Garden Acres Bridge is a six lane principal arterial on the City's Master Thoroughfare Plan with bike lanes on the City's Bike Fort Worth Plan.  The Garden Acres Bridge project includes the construction of an additional three lane bridge structure parallel and adjacent to the existing bridge.  The second bridge will provide additional capacity which will help to minimize congestion and traffic delays.  The project will also increase safety by providing protected left turn lanes, bike lanes, sidewalks and new traffic and pedestrian signals.  In conjunction with the new bridge there will be minor upgrades to the existing three lane bridge to increase its capacity.

Under Amendment No. 6, URS Corporation (URS) (n/k/a AECOM) will perform additional Construction Phase Services as necessary.  The table below recites the contract and amendment history.  URS proposes to complete Amendment No. 6 for a not-to-exceed amount of $44,784.00.  Staff considers this fee to be fair and reasonable for the additional scope of services.

Under an Advance Funding Agreement for construction Mayor and Council Communication (M&C C-27677), City Council authorized execution of an Agreement with TxDOT with City participation in the amount of $1,438,227.00.  Construction started on this project in January 2017 with estimated completion in August 2018.


-

Amount

Project Description

M&C No.

Approved

Initial Contract

$485,932.58

Design of Garden Acres Bridge over I-35W Expansion.

C-25611

05/15/2012

Amendment 1

$ 28,660.00

Add sidewalks to the plans, specification and cost estimates.

Approved Administratively

01/02/2013

Amendment 2

$ 74,500.00

Level of service Analysis, preparation of design schematic and surveying required by TxDOT.

C-26487

10/07/2013

Amendment 3

$125,500.00

Additional bridge design as required by TxDOT for the new & existing bridges

C-27095

12/02/2014

Amendment 4

$104,077.95

Noise Analysis as required by TxDOT and additional Traffic Analysis Landscaping, Environmental and Construction Services.

C-27677

04/12/2016

Amendment 5

$114,035.00

Construction Phase Services as required.

C-28135

03/07/2017

Amendment 6

$44,784.00

Additional Construction Phase Services as required.

With This   M&C

With This M&C

Total

$977,489.53

-

-

-



























This project is located in COUNCIL DISTRICT 6.

 
FISCAL INFORMATION/CERTIFICATION:

The Director of Finance certifies that funds are available in the 2008 Street Improvements Fund.  Prior to an expense / expenditure being incurred, the participating department has the responsibility to validate the availability of funds.

TO
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

FROM
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

Submitted for City Manager's Office by:
Jay Chapa (5804)
Originating Department Head:
Douglas Wiersig (7801)
Additional Information Contact:
Wilma Smith (8785)

 
 