COUNCIL ACTION:  Approved on 10/17/2017 

DATE: 10/17/2017 REFERENCE NO.: C-28440 LOG NAME: 21WEST PATROL DIVISION CONSTRUCTION
CODE: C TYPE: NON-CONSENT PUBLIC HEARING: NO
SUBJECT:  

Authorize Execution of Construction Contract with Balfour Beatty Construction, LLC, in the Amount of $1,691,344.00, Including 7.5 Percent for the Owner's Construction Contingency Allowance for the New West Patrol Division, a Remodel of an Existing Facility Located at 3532 Joyce Drive and Provide for Administrative Costs in the Amount of $1,382,083.00 for a Total Project Cost of $3,230,000.00 (CCPD Funded) (COUNCIL DISTRICT 3)


RECOMMENDATION:

It is recommended that the City Council authorize the execution of a construction contract with Balfour Beatty Construction, LLC, in the amount of $1,691,344.00, including 7.5 percent for the Owner's Construction Contingency Allowance for the new West Patrol Division, a remodel of an existing facility located at 3532 Joyce Drive and provide for administrative costs in the amount of $1,382,083.00 for a total project cost of $3,230,000.00.

 
DISCUSSION:

The Police Department's West Patrol Division is currently housed in two facilities.  Land and facilities totaling 3.290 acres on Joyce Drive was purchased in March of 2014 (M&C C-26688) to provide for a new West Division Headquarters.  The City engaged Elements of Architecture through the annual architectural Agreement to redesign the existing facility and to produce drawings and bid documents for the new headquarters.  

The City issued a Request for Proposals to prospective contractors on June 22 and 29, 2017.  Pre-proposal meetings and site visits were conducted with interested contractors.  On August 4, 2017, the City received eight responses from general construction contractors.  Five of these firms provided the required Post Proposal–Pre Award Submittals to be further evaluated by the City.  Those firms were:

  • Azteca Enterprises, Inc.
  • Balfour Beatty Construction, LLC
  • CPM Commercial Construction, Inc.
  • Denco CS Corp
  • RJM Contractors, Inc.

These proposals were reviewed by members of the Police Department, Office of Business Diversity and the Property Management Department and were evaluated for best value based on the criteria set forth in the Request for Proposals.  The selection team recommends award of the construction contract to Balfour Beatty Construction, LLC.

Criteria

Balfour Beatty Construction, LLC

RJM Contractors, Inc.

CPM Commercial Construction, Inc.

Denco CS Corp

Azteca Enterprises, Inc.

Proposed Price

60

59

59

55

49

M/WBE

6.5

6.0

6.5

6.5

7.0

Proposed Schedule

7

5

5

4

10

Reputation/Experience

9

9

9

8

5

Past Relationship with City of Fort Worth

5

7

5

5

6

TOTAL

87.5

85.0

83.5

77.5

77.0

The overall project costs are expected to be as described in table below:

WEST PATROL DIVISION PROJECT BUDGET

TOTALS

Architectural and Engineering Design

$   121,040.00

Project Management, Existing Condition Survey, Bid Advertisement, etc.

$     35,532.00

Design Phase Total

$   156,572.00

Construction Contract (Including Alternates 2, 3, 4, 5, 6 & 7 and 7.5 percent of Base Bid as Owner's Construction Contingency Allowance)

$1,691,344.00

Project Administration Cost:  IT, Security, Site Fencing, Project Management, Contingency, FFE, Etc.

$1,382,084.00

Construction Phase Total

$3,073,428.00

PROJECT TOTAL

$3,230,000.00


In accordance with Chapter 7, Article III, Section 7-47, Section 109.2.1 of the City Code, Building and Trade Permit Fees are waived for this project.

Construction is anticipated to start in Fall 2017, with an anticipated completion date during the Summer of 2018.

FUNDING SOURCES -  This project is funded through the CCPD Facility Budget FY15 and FY16.

M/WBE OFFICE - Balfour Beatty Construction, LLC is in compliance with the City's BDE Ordinance by committing to 16 percent MBE participation on the base bid.  The City's MBE goal on this project is 15 percent.

The West Patrol Division Office will be located in COUNCIL DISTRICT 3.
 
FISCAL INFORMATION/CERTIFICATION:

The Director of Finance certifies that upon approval of the above recommendations, funds will be available as appropriated of the CCPD Capital Projects Fund.  Prior to an expenditure being made, the participating department has the responsibility to validate the availability of funds.











TO
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

FROM
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

Submitted for City Manager's Office by:
Jay Chapa (5804)
Originating Department Head:
Steve Cooke (5134)
Additional Information Contact:
Brian Glass (8088)

 
 
ATTACHMENTS
  Form 1295 Balfour Beatty.pdf
  West Patrol Division.pdf