Official site of the City of Fort Worth, Texas |
City Council Agenda | |
COUNCIL ACTION: Approved on 6/20/2017 - Ordinance No. 22790-06-2017 | |||||
DATE: | 6/20/2017 | REFERENCE NO.: | C-28289 | LOG NAME: | 20HEMPHILL CMAR GMP |
CODE: | C | TYPE: | NON-CONSENT | PUBLIC HEARING: | NO |
SUBJECT: | Authorize Amendment No. 3 to City Secretary Contract No. 45717, the Construction Manager-at-Risk Agreement with McCarthy Building Companies, Inc., Establishing the Guaranteed Maximum Price in the Amount Not to Exceed $37,477,446.00 for the Construction of the Hemphill Street Connector Project, Provide for Additional City Project Costs and Adopt Appropriation Ordinance (COUNCIL DISTRICT 9) |
RECOMMENDATION: | ||||||||||||||||||||||||||||||||||||||||
It is recommended that the City Council: 1. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations of the Intergovernmental Contribution Fund in the amount of $3,448,803.00 from Regional Toll Revenue Funds from the Texas Department of Transportation (TxDOT); and 2. Authorize Amendment No. 3 to City Secretary Contract No. 45717 with McCarthy Building Companies, Inc., establishing the Guaranteed Maximum Price in the amount not to exceed $37,477,446.00 for the construction of the Hemphill Street Connector Project. |
||||||||||||||||||||||||||||||||||||||||
DISCUSSION: | ||||||||||||||||||||||||||||||||||||||||
The Guaranteed Maximum Price (GMP), in the amount of $37,477,446.00, consists of two work efforts: Final Works Package - $35,408,258.00, which is subdivided into two work phases; Railroad Bridge Phase for the construction of the railroad track and bridge, excavation, and retaining walls and the Roadwork Phase - for the construction of electrical, roadway paving, and landscaping to complete the project; and the Stormwater Facilities Early Works Package, Mayor and Council Communication (M&C C-27065) - $2,069,188.00, which was completed in July 2015. Additional City project costs, in the amount of $1,755,000.00, are needed resulting in a total construction work effort in the amount of $39,232,446.00. On April 6, 2017 and April 13, 2017, McCarthy advertised the Final Works Package components in the Fort Worth Star-Telegram, as well as employed enhanced measures to alert the North Texas contracting community of this bidding opportunity. In addition, McCarthy hosted a Minority Business Enterprise outreach event on April 18, 2017 and conducted a Pre-Construction Conference on April 21, 2017. On May 10, 2017 bids were received and evaluated by McCarthy based on published factors such as ability to start and complete the project within the project schedule, construction techniques and the ability to perform the work and other specific criteria including but not limited to the following: • Cost Contractors have been recommended by McCarthy to Staff as offering the best value to McCarthy and the City, with which Staff concurs. While McCarthy Building Companies, Inc. is the recommended contractor, the Director of Transportation and Public Works has determined that McCarthy Building Companies, Inc., provides the best value for the City.
Funding sources for the Project are as follows:
Amounts rounded for presentation purposes. ** Not included in the project's appropriated budget. M/WBE OFFICE - McCarthy Building Companies, Inc., is in compliance with the City's BDE Ordinance by committing to 15 percent MBE participation for the overall Project. The City's MBE goal on this project is 15 percent. The Hemphill Street Connector project is located in COUNCIL DISTRICT 9, Mapsco 76D and 76H. |
||||||||||||||||||||||||||||||||||||||||
FISCAL INFORMATION/CERTIFICATION: | ||||||||||||||||||||||||||||||||||||||||
The Director of Finance certifies that upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the current capital budget of the Intergovernmental Contribution and Street Improvements Supplemental Funds for the Hemphill Street Connection Project (C00141) for Fiscal Year 2017. |
|
|||||||||||||||||||||
|
Submitted for City Manager's Office by: |
|
Originating Department Head: |
|
Additional Information Contact: |
|
|
ATTACHMENTS |
20HEMPHILL CMAR CONSTRUCTION MAP.pdf |
20HEMPHILL CMAR GMP _30106_AO17.docx |
Form 1295 Certificate 100217541 GMP2.pdf |
Rev. List of Bidders 5-10-17.pdf |