COUNCIL ACTION: Approved on 6/20/2017 - Ordinance No. 22786-06-2017 | |||||
DATE: | 6/20/2017 | REFERENCE NO.: | **C-28281 | LOG NAME: | 20HMAC (2015-5) HIR STREET REHABILITATION |
CODE: | C | TYPE: | CONSENT | PUBLIC HEARING: | NO |
SUBJECT: | Authorize Additional Street Segments of North Hill Lane and North Commerce Street to City Secretary Contract No. 47193 with Cutler Repaving Inc., with No Increase to the Contract Amount, Provide for Additional Staff and Project Costs of $102,450.00 for a Revised Project Amount of $4,379,656.65 and Adopt Appropriation Ordinance (COUNCIL DISTRICT 2) |
RECOMMENDATION: | ||||||
It is recommended that the City Council: 1. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water Capital Projects Fund in the amount of $81,450.00 in the HMAC 2015-5 Hot-In-Place Reconstruction from available funds for the addition of the North Hill Lane and North Commerce Street rehabilitation street segments; and |
||||||
DISCUSSION: | ||||||
On September 15, 2015, (M&C C-27464) the City Council authorized the execution of a contract with Cutler Repaving Inc., in the amount of $3,714,606.65 for Hot Mix Asphaltic Concrete (2015-5) HIR Street Rehabilitation. Two additional street segments will be added to the contract in conjunction with separate utility contracts for the replacement of water lines and storm drains. The Transportation and Public Works Department and the Water Department share in these rehabilitation costs in lieu of permanent trench repair, under the utility contract. The street segments that will be added to the contract are listed in the table below. Quantity underruns in the initial street segments of City Secretary Contract No. 47193 have provided the capacity to add these two street segments without increasing the existing contract amount. Funding to cover the cost of the rehabilitation on these two added street segments will be appropriated from the Water Capital Project Fund and transferred from the available balance in Stormwater Cap Project Bond Fund of the existing Greenfield Acres Drainage Improvement Project. The contract time will be extended by 59 calendar days to complete these two additional streets.
M/WBE OFFICE: Cutler Repaving, Inc., is in compliance with the City's DBE Ordinance by committing to 10 percent MBE participation on this project. The City's MBE goal on this project is 10 percent These projects are located in COUNCIL DISTRICT 2, Mapsco 46M and 62Q. This contract will have no impact to future operating budgets for TPW Department. |
||||||
FISCAL INFORMATION/CERTIFICATION: | ||||||
The Director of Finance certifies that funds are available in the current capital budget, as appropriated, of the Stormwater Cap Project Bond Fund, and upon approval of the above recommendations and adoption of the attached Appropriation Ordinance, funds will be available in the current capital budget, as appropriated, of the Water Capital Projects Fund. The Fiscal Year 2017 Water Operating Budget includes appropriations of $21,060,000.00 for the purpose of providing Pay-As-You-Go Funding for Water Capital Projects. After this transfer for Fiscal Year 2017, the balance will be $4,586,966.00 |
|
|||||||||||||||||||||
|