M&C Review


COUNCIL ACTION:  Approved on 12/13/2016 - Ordinance No. 22558-12-2016, 22559-12-2016, 22560-12-2016 & 22561-12-2016

DATE: 12/13/2016 REFERENCE NO.: C-28054 LOG NAME: 20BONDS RANCH IMPROVEMENTS
CODE: C TYPE: NON-CONSENT PUBLIC HEARING: NO
SUBJECT:   Adopt Appropriation Ordinances in the Collective Amount of $2,800,335.89 for the Construction of Intersection and Drainage Improvements at Bonds Ranch Road and US 287 (COUNCIL DISTRICT 7)

RECOMMENDATION:

1.  Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Bonds Ranch Road Intersection Improvements Project in the 2007 Critical Capital Projects Fund in the amount of $114,224.31 and reduce the balance in reserves by the same amount for the construction of the Intersection and Drainage Improvements at Bonds Ranch Road and US 287;

2.  Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the in Bonds Ranch Road Intersection Improvements Project in the Street Improvements 2008 Fund in the amount of $212,552.78 and reduce the balance in the fund reserves by the same amount for the construction of the Intersection and Drainage Improvements at Bonds Ranch Road and US 287;

3.  Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the in Bonds Ranch Road Intersection Improvements Project In the Street Improvements Supplemental Fund in the amount of $73,558.80 and reduce the balance in the fund reserves by the same amount for the construction of the Intersection and Drainage Improvements at Bonds Ranch Road and US 287; and

4.  Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Bonds Ranch Road at US 287 Project of the Transportation Impact Fee Capital Fund in the amount of $2,400,000.00 and reduce the fund balance in the Unspecified Center of Service Area C by the same amount.

 
DISCUSSION:

On June 28, 2016 (M&C C-27802) the City Council authorized execution of an Engineering Design Agreement with Kimley Horn and Associates in for design services of drainage and paving improvements along Bonds Ranch Road from the Burlington Northern Santa Fe Railroad crossing to FM 156 and an appropriation ordinance in the amount of $500,000.00 to initially fund the project. The first phase of the project which provides interim single lane roundabouts on Bonds Ranch Road at US 287 was scheduled to begin construction this summer with the provision that the Texas Department of Transportation (TxDOT) was providing all materials for the project.

It became apparent in July, during discussions with TxDOT, that due to their procurement process and fiscal commitments, they could not deliver materials for this project to move forward as scheduled.  At that point, the City made the decision to appropriate the necessary funds to furnish the materials and utilize a combination of street services personnel and a task order contractor (The Fain Group, City Secretary Contract No. 48262) to assist in the timely construction of Phase 1 improvements, which began November 1, 2016.  

Additional funding for the project is required and has been identified from several sources:  completed Intersection Improvement projects from the 2007 Critical Capital Program, the 2008 Bond Program and Supplemental CO Funds, 2014 Bond Program Intersection Improvement Funds and funds from the Transportation Impact Fee Capital Fund.  This project will improve safety and traffic operations along this corridor in advance of an anticipated 200,000 square feet of commercial development.

This construction is one component of the overall project that includes design, project management and contingencies. The overall project budget is $4,130,388.61.      

This project is in COUNCIL DISTRICT 7.

This M&C does not request approval of a contract with a business entity.

 
FISCAL INFORMATION/CERTIFICATION:

The Director of Finance certifies that upon approval of the above recommendations and adoption of the attached Appropriation Ordinances, funds are available in the current capital budgets, as appropriated, of the 2008 Street Improvement Fund, 2014 Bond Funds, Developer Contribution Fund, 2007 Critical Capital Fund, Street Improvement Supplemental Fund and The Transportation Impact Fee Capital Fund.
  

Description

Existing Appropriations

Additional Appropriations per M&C

Proposed Appropriation

General Capital Fund 30100

$     72,918.30

$              0.00

$     72,918.30

Transportation Impact Fee Fund   39008

$   500,000.00

$2,400,000.00

$2,900,000.00

2007 Critical Capital Fund - 39001

-

$    114,224.31

$   114,224.31

Street Improvements 2008 Fund 39407

-

$   212,552.78

$  212,552.78

Street Improvements Supplemental Fund 39406

-

$     73,558.80

$   73,588.80

2014 Bond Program Fund 34014

$   733,098.39

$               0.00

$   733,098.39

Totals        

$1,306,016.69

$2,800,335.89

$4,106,405.30


TO
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

FROM
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

Submitted for City Manager's Office by:
Jay Chapa (5804)
Originating Department Head:
Douglas Wiersig (7801)
Additional Information Contact:
Todd Estes (5441)

 
 
ATTACHMENTS
  20BONDS RANCH ROAD AO 1.docx
  20BONDS RANCH ROAD AO 2.docx
  20BONDS RANCH ROAD AO 3Rev.docx
  20BONDS RANCH ROAD AO 4.docx