COUNCIL ACTION:  Approved on 6/28/2016 

DATE: 6/28/2016 REFERENCE NO.: **C-27808 LOG NAME: 20SW_LOWER COMO_CONSTRUCTION
CODE: C TYPE: CONSENT PUBLIC HEARING: NO
SUBJECT:  

Authorize Execution of a Contract with Austin Filter Systems, Inc., in the Amount of $611,638.00 for the Construction of Lower Como Erosion Control Improvements and Provide for Contingencies and Construction Services for a Total Construction Amount of $724,818.00 (COUNCIL DISTRICT 3)          


RECOMMENDATION:

It is recommended that the City Council authorize the execution of a contract with Austin Filter Systems, Inc., in the amount of $611,638.00 for the construction of Lower Como Erosion Control Improvements.

 
DISCUSSION:

The purpose of this Mayor and Council Communication is to authorize the execution of a contract with Austin Filter Systems, Inc., in the amount of $611,638.00. This project will alleviate substantial and progressing creek erosion that poses a risk to public infrastructure in the Lower Como Creek and is causing property damage in the back of residential property along Driskell Boulevard.

The project was advertised for bid in the Fort Worth Star-Telegram on March 17, 2016 and March 24, 2016. On April 14, 2016, the following bids were received:

BIDDERSBID AMOUNT
Austin Fitter Systems, Inc.$611,638.00
The Fain Group, Inc.$737,279.50

It is recommended that a contract be awarded in the amount of $611,638.00 to Austin Filter Systems, Inc. Costs for the implementation of this project will be funded by the Stormwater Capital Projects Bond Fund.

The recommended contract award amount includes a pre-established field order allowance (construction allowance) of $26,500.00. Other budget items beyond the construction contract amount include $76,180.00 for construction management, survey, material testing, and inspection, and $37,000.00 for contingencies. The total construction budget is $724,818.00. Construction is anticipated to start in August 2016 and end in February 2017. This project will result in no additional impact to the Transportation and Public Works Department annual operating budget.

M/WBE Office - Austin Filter Systems, Inc., is in compliance with the City's BDE Ordinance by committing to 11 percent MBE participation.  The City's MBE goal on this project is 11 percent.

This project is located in COUNCIL DISTRICT 3, Mapsco 75P.

 
FISCAL INFORMATION/CERTIFICATION:

The Director of Finance certifies that funds are available in the current capital budget, as appropriated of the Stormwater Capital Projects Bond Fund.

  

Fund Source

Appropriation Amount

Encumbrances

Remaining Budget

Stormwater Capital Projects (52002)

$100,000.00

$0.00

$100,000.00

Stormwater Capital Projects – Bonds (59651)

$1,321,303.68

$24,370.38

$782,879.40

Stormwater Capital Projects (59652)

$61,200.32

$0.00

  $57,434.97

Total

$940,314.37

TO
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount

FROM
    Fund Department
ID
Account Project
ID
Program Activity Budget
Year
Reference #
(Chartfield 2)
Amount
    59651 0200431 5740010 C01605   C02883     $611,638.00

Submitted for City Manager's Office by:
Jay Chapa (5804)
Originating Department Head:
Douglas Wiersig (7801)
Additional Information Contact:
Raul Lopez (2457)

 
 
ATTACHMENTS
  CP 01605 Form HB1295.pdf
  CP 01605 Map.pdf